Abstract: This document is a dedicated closed-loop management SOP for mold abnormal issues implemented with the Fangtian MOLDERP system. It uses the mold project number and abnormal work order number as unified cost collectors, covering the full business chain: abnormal issue reporting, tiered review, root cause analysis, corrective action notice issuance, ECN engineering changes, synchronized BOM/process card updates, outsourced purchase requisition, rework work order scheduling, trial molding verification, COPQ material/labor/expense collection, and improvement horizontal deployment. It distinguishes internal quality abnormalities from customer engineering changes, adapts to the single-unit non-standard project manufacturing characteristics of molds, and connects the data closed loop across MOLDERP, APS advanced scheduling, and IMES operation reporting, enabling traceable mold abnormalities, clear responsibility assignment, and automatic loss calculation.
This SOP applies to quality abnormalities arising in mold enterprises during machining, assembly, trial molding, incoming material inspection, and mold return to factory scenarios, including design-related, machining-related, assembly and fitting-related, trial molding-related, and incoming material-related abnormalities.Customer engineering changes are managed as a separate category and are not included in internal COPQ quality costs; they follow the customer change quotation process.

Core main system:Fangtian MOLDERP Mold Management SystemSupporting collaborative modules: ECN engineering change management, BOM version management, process card management, APS advanced scheduling, IMES manufacturing execution reporting, cost accounting module, supplier claim management, and mold history management. Core identifier:abnormal work order number (cost collector)—all documents across the entire chain are mandatorily linked to it, serving as the sole carrier for COPQ collection.
Single-unit project system: one mold corresponds to an independent project number and independent version-controlled BOM.
Version locking: BOM, drawings, and process card versions are strongly bound; old versions are prohibited from initiating purchase requisitions, material issuance, or work reporting.
Incremental accounting: only additional costs caused by the abnormality are counted; baseline mold manufacturing costs are not included in abnormal losses.
Trial molding gate: T-sequence trial molding report plus customer signed sample (when necessary) is a prerequisite for closing an abnormality.
Responsibility allocation: the corrective action notice simultaneously locks in the responsible party and allocation ratio, supporting supplier deductions and departmental quality assessments.
| Code | Category | Typical Abnormal Scenarios | Primary Responsible Department |
|---|---|---|---|
| D | Design | Structural interference, insufficient draft angle, cooling water channel interference, incorrect shrinkage factor selection, insufficient slide stroke | Mold Design Department |
| M | Machining | Overcut/undercut, datum misalignment, heat treatment deformation/cracking, incorrect EDM spark gap, wire-cut taper out of tolerance | Machining Workshop (CNC/EDM/Heat Treatment) |
| A | Assembly and Fitting | Mold matching step difference, excessive clearance, slide jamming, ejector pin whitening, water channel leakage, poor die spotting | Fitter Assembly Team |
| T | Trial Molding | Sink marks, flash, sticking, short shot, weld lines, product dimension chain out of tolerance, burning/deformation | Trial Molding Team, Injection Molding Process |
| S | Incoming Material | Mold base geometric tolerance nonconformance, steel material/hardness mismatch, standard part failure | IQC, Purchasing Department |
| E | Customer Engineering Change | Product structure change, cavity count change, steel upgrade, mandatory customer mold modification request | Project Department (separate process, not included in COPQ) |
| Level | Judgment Criteria | Response Time | Corrective Action Notice Issuance Deadline | Maximum Closure Period | Review Organization |
|---|---|---|---|---|---|
| A - Major | Estimated loss ≥ RMB 50,000, impact on delivery, customer production line stoppage, mold scrapping risk, need to re-run PPAP, mold return to factory | 2-hour rapid response | 24 hours | 15 days | Plant Manager + Project + QE + Design |
| B - General | Part remanufacturing or rework, impact on process progress, estimated loss RMB 5,000–50,000 | 4-hour response | 48 hours | 7 days | QE + Design + Workshop Supervisor |
| C - Minor | Can be quickly resolved on site, no impact on delivery, estimated loss < RMB 5,000 | Same shift response | Centralized review at weekly meeting | 3 days | QE + Team Leader |
Complete chain: on-site containment and version freeze → submit [Mold Abnormal Issue Report] in MOLDERP → tiered review & root cause analysis → responsibility determination & cost allocation → system issuance of [Abnormal Corrective Action Notice] → design initiates ECN change, updates BOM + process card → Branch 1 [Outsourced replacement: purchase requisition → procurement → IQC → warehouse receipt → kit issuance] / Branch 2 [Rework and repair: rework work order issuance → APS scheduling → IMES operation reporting + operation inspection] → fitter assembly and fitting → trial molding verification → abnormal closure verification → system automatically collects COPQ material/labor/expense losses → improvement horizontal deployment, writing into mold history, document archiving
Place red-tag quarantine on defective parts on site, count work-in-progress and same-cavity symmetrical parts, and assess the scope of related impact.
Quality QE freezes thecurrent BOM version and process card version of the mold in MOLDERP.
System control: frozen versions cannot create new work orders, generate purchase requisitions, or issue materials from the warehouse, preventing secondary scrapping caused by continued processing per the old version.
Output records: quarantine records, version freeze logs, and related part impact assessment form.
Reporting roles: fitter, trial molding operator, QC, IQC, machining team leader. System mandatory fields: mold project number, mold number, cavity count, abnormal part number + version, discovery operation, equipment number, occurrence time, trial molding T-sequence, defect description, measured values, drawing standard, photo attachments, delivery impact assessment, temporary containment measures. Routing rules: after submission, the document is automatically pushed to Quality QE for preliminary review; invalid abnormalities can be directly rejected with a reason noted.
QE leads the review notice initiated within the MOLDERP abnormal document, pushing it to design, workshop, project, and purchasing personnel.
Root cause analysis tools: 5Why, fishbone diagram, 8D. Fixed analysis dimensions for the mold industry: design parameters, raw material heat treatment, machining datum process, equipment and tooling, measurement compensation.
Review conclusions are entered into the system: root cause description, corrective action type (mold modification / part replacement and remanufacturing / concession acceptance / scrapping and re-opening the mold), acceptance criteria, and correction deadline.
Solution determination branches: ① replacement with new outsourced part; ② rework and repair of the original part; ③ outsourced processing.
Responsibility is determined based on MOLDERP historical records: drawing version logs, operation reporting records, incoming inspection documents, and historical ECN records.
Enter the responsible party in the system: internal department / outsourced vendor / raw material supplier; fill in the allocation ratio.
Rules: for S-type incoming material abnormalities, a supplier claim document is simultaneously created in MOLDERP, and subsequent purchasing deductions are automatically written back to offset losses; E-type customer engineering changes follow the separate quotation process and arenot included in internal COPQ statistics.
Output: responsibility determination opinion, bound to the abnormal document and not arbitrarily modifiable.
After the review is approved, QE issues the corrective action notice in the system, automatically carrying the associated abnormal report number.
The system automatically generates theabnormal work order number (cost collector), and all downstream documents (purchase requisitions, rework work orders, outsourced processing orders, material requisition orders, work reports, warehouse receipt orders) must be linked to this number.
Documents are automatically distributed to: executing responsible unit, mold design, planner, and cost accountant.
Key fields: corrective action plan, planned completion milestone, acceptance criteria, and responsibility allocation ratio.
This step is the core hub of the entire closed loop, achieving consistent version control across drawings, BOM, and process.
Design receives the corrective action notice and initiates the change in the MOLDERP [ECN Engineering Change Module].
Update the mold BOM: part version upgrade/new part number, mark the disposal method of old parts (scrap / repurpose / return), and automatically assess synchronized changes to associated matching parts such as slides, lifters, and inserts.
Revise the process card: update operation routing, machining allowance, datums, heat treatment, EDM spark gap, and inspection control points.
The system automatically derives downstream documents:
standard purchased parts and steel raw materials → generate material purchase requisitions;
self-manufactured rework parts → generate rework work orders;
outsourced operations such as heat treatment and large surface grinding → generate outsourced processing orders.
Version verification: after the ECN is reviewed and effective, the version numbers of drawings, BOM, and process cards are synchronously updated, and old versions are locked.
Purchase requisition approval: supervisor reviews necessity, cost budget verification, and purchasing confirms delivery; urgent items are marked with an expedite flag.
Procurement operations: inquiry and price comparison, purchase order PO issued in the system, with material certificates, ultrasonic testing, and hardness inspection requirements bound.
IQC incoming inspection: steel spectroscopy, hardness, and mold base geometric tolerance verification; nonconforming incoming materials trigger a new incoming material abnormal document in MOLDERP.
Warehouse receipt: new-version parts are received into the warehouse, and the system locks old-version parts to prohibit issuance.
Kit issuance: the warehouse issues materials as a complete kit per the rework work order; missing parts are intercepted by the system to prevent issuance, avoiding idle waiting time being counted into abnormal losses.
The new-version process card is issued to the workshop along with the rework work order.
The planner pushes the rework work order to the Fangtian APS advanced scheduling module.
APS scheduling constraints: prioritize locking bottleneck resources of 5-axis CNC, slow wire cutting, EDM, and heat treatment, while incorporating electrode manufacturing lead time, and schedule backward from the trial molding milestone.
The workshop performs QR code work reporting in IMES, with working hours divided into three categories: machining hours, waiting hours (waiting for material/electrode/heat treatment), and inspection hours.
Operation inspection checkpoints: inspection points are set after finishing machining, EDM, and heat treatment; nonconformances are directly routed back to the abnormal process flow.
Fitters assemble and fit per the new-version BOM, perform water channel pressure testing, and ejection reset verification.
Submit a trial molding application in MOLDERP, generate a trial molding report, and record molding defects and measured product dimensions.
Verification determination: dimensions and molding condition meet requirements; where customer confirmation is required, the customer signed sample file must be uploaded.
Pre-closure verification (system mandatory check; closure is prohibited if documents are missing): abnormal report, corrective action notice, ECN change order, new-version BOM & process card, purchase/warehouse receipt/material requisition documents, rework work report, trial molding report, and loss calculation sheet.
Verification NG: do not close; re-review the solution, add a second correction record, and all costs continue to be collected under the same abnormal work order number.
The system uses the abnormal work order number as the collector for automatic aggregation; the cost accountant performs review, and automatic allocation by responsibility ratio is supported.
Only incremental costs are counted.
Scrapped semi-finished parts are valued using thecumulative operation cost method(not raw material unit price).
Residual value, supplier claim recoveries, and customer charges are treated as offsetting items.
Material loss = Σ cumulative operation cost of scrapped parts − scrap residual value + cost of newly purchased materials at plant + electrode/auxiliary material/trial molding material consumption ± offset for repurposed old parts
Labor loss = Σ abnormal-related working hours × operation labor rate (review, design change, disassembly/assembly, rework, mold follow-up; overtime weighted at 1.5–2 times; normal machining hours are not counted)
Expense loss = Σ machine-hour cost (depreciation + energy + maintenance) + outsourced processing cost + inspection cost + expedited logistics cost + customer re-sampling/penalty − supplier claim recoveries
Total COPQ loss for this occurrence = material loss + labor loss + expense loss
The accounting result is automatically written back to the abnormal document and supports export of the "Mold Abnormal Correction Loss Accounting Sheet" for departmental assessment and supplier performance evaluation.
Quality enters improvement countermeasures and synchronously updates the MOLDERP design standard library, machining standard library, and inspection standard.
Horizontal deployment control: register same-series molds, other molds under the same project, and same-supplier lists in the system, and track prevention of similar issues.
All abnormal documents are automatically archived, and abnormal records, correction counts, T-trial counts, and cumulative COPQ costs are written into the [Mold History Card]. The mold history can be used for new project quotation risk assessment and historical issue tracing.
Without an effective corrective action notice, ECN changes are not allowed to be initiated.
If the ECN has not been reviewed and made effective, BOM/process card versions are not updated, and purchase requisitions and rework work orders cannot be generated.
Old-version BOM and process cards are locked, prohibiting material issuance and work reporting.
If the abnormal document has not completed trial molding verification or lacks the full set of attachments, the system prohibits closing the abnormality.
All downstream documents must be linked to the abnormal work order number; unlinked documents cannot be collected into the COPQ report.
E-type customer engineering change documents are independently flagged and automatically isolated, not participating in internal quality cost statistics.
Mold abnormal ledger (filterable by level, category, time period, and responsible department)
COPQ quality cost summary table (material/labor/expense breakdown)
Supplier abnormal loss and claim recovery statistics table
Mold history report (mold modification count, T-trial count, cumulative correction cost)
First trial molding success rate FTT and average mold modification count statistics report
Abnormal closure cycle SLA achievement rate report
| No. | Risk Point | Consequence | MOLDERP Control Countermeasure |
|---|---|---|---|
| 1 | Continuing processing without freezing BOM | Repeated scrapping | One-click version freeze after abnormal reporting; system intercepts old-version operations |
| 2 | Scrapped parts only valued at raw material price | Loss underestimation | System automatically values semi-finished product costs using cumulative operation cost method |
| 3 | Waiting hours not collected | Delivery responsibility misjudged | IMES work reporting mandates distinction between machining/waiting hours, separately counted |
| 4 | Customer engineering changes mixed into internal abnormalities | Distorted cost assessment | Category code isolation; E-type documents automatically excluded from COPQ |
| 5 | Closing without signed sample | Batch customer-side defects | System requires uploaded signed sample attachment as closure verification item |
| 6 | Supplier claims without closed loop | No supplier quality improvement | Claim document bound to abnormal document; deduction completion automatically writes back to offset losses |
Q1: What is the difference between the Fangtian MOLDERP mold abnormal closed-loop SOP and a general ERP abnormal process? A1: It is specifically designed for mold project-based manufacturing, binding ECN, BOM versions, and trial molding T-sequences; connecting APS rework scheduling and IMES operation reporting; supporting cumulative operation cost accounting for semi-finished products; and automatically outputting COPQ quality costs—distinct from the nonconforming product process of mass production manufacturing.
Q2: In MOLDERP, must ECN changes be triggered by abnormal corrective action notices? A2: In the scenario of this SOP,mold modification ECNs caused by quality abnormalities must be linked to the corrective action notice; customer-initiated engineering change ECNs follow the independent change process and are not bound to quality abnormal documents.
Q3: What are the differences between rework work orders and normal machining work orders in MOLDERP? A3: Rework work orders are mandatorily linked to the abnormal work order number, with costs collected into COPQ; when pushed to APS, they receive higher scheduling priority; IMES work reporting marks them as rework hours, separately distinguished in reports.
Q4: Can COPQ loss accounting be automatically allocated to design, machining, and suppliers? A4: Yes. The allocation ratio is pre-entered in the corrective action notice, and the MOLDERP cost module automatically splits losses by ratio, supporting departmental quality assessment and supplier deductions.
Q5: Can this process be integrated with the entire Fangtian T-ONE, MOLDERP, APS, and IMES smart manufacturing platform? A5: Yes. This SOP is the standard business process of the Fangtian mold digitalization platform, with documents, working hours, and cost data linked in real time across modules.