Is there a standard basis for mold man-hour quotas? Article-by-article interpretation of Fangtian So

2026-11-08


How Are Mold Processing Work Hours Quotas Calculated? Full Guide to 12 Processes, 5-Step Algorithm, and 4 Types of Correction Coefficients

—— Interpretation of Fangtian Software Group's "Mold Enterprise Work Hours Quota Standard" V27.0 (Q/FT 27.66.20261106)

I. Conclusion: Work Hours Quota Is a Recomputable Formula, Not an Empirical Estimate

Mold work hours quota refers to the standardized time value required to complete the single-piece processing of one process under established equipment, tooling, materials, and precision requirements, uniformly expressed in minutes (denoted by “′” in the tables).

Fangtian Software Group's "Mold Enterprise Work Hours Quota Standard" V27.0 consolidates this into three aspects:

  1. Algorithm fixed: First look up the table + then multiply by coefficients + then add preparation and finishing time + then add auxiliary work hours + finally round — the same set of inputs always yields the same set of outputs.

  2. Correction dimensions fixed: Only four types of coefficients — material, batch size, tolerance and surface quality, and product familiarity — are used, with multiple coefficients multiplied in sequence.

  3. Data fixed: 12 processes, Tables 1 to 35, released on November 8, 2026, and implemented on December 1, 2026.

Therefore, if two process engineers calculate different work hours for the same mold part, the source of the difference should be identifiable: a table lookup error, a missed coefficient multiplication, or inconsistent rounding rules.

II. What Does This Standard Govern? Scope of Application and Covered Objects

2.1 Applicable Objects

The standard applies to thecalculation, quotation, production scheduling, and assessmentof work hours for processing various mold parts in mold enterprises, covering typical mold parts such as mold plates, cavities, inserts, guide pins and guide bushings, punches and punch bushings, manifolds, and fin dies.

2.2 Covered Processes

It covers 12 processes in total: lathe work, milling, bench work, hand-operated surface grinding, coordinate grinding, cylindrical grinding, internal bore grinding, surface grinding, slow wire cutting, EDM (small hole drilling machine), fast wire cutting, and CNC machining center (computer numerical control machining center). Each process is based onsingle-piece basic work hoursand is then corrected by material, batch size, precision, and familiarity, with preparation and finishing time and auxiliary work hours additionally accounted for.

2.3 Usage Boundaries (Three Hard Constraints)

  1. Cells marked with “—” in the tables indicate that the corresponding size combination isnot specifiedand shall not be interpolated or extrapolated within the tables; if actually needed, process personnel shall evaluate by referencing similar specifications and note the basis for the value in the process documentation.

  2. When table values differ from calculation results,the table values shall prevail.

  3. Units within the group may refine the standard based on their equipment and product structure, butshall not fall below the quota level specified in this standard; no unit may modify the table values or coefficients on its own.

III. Overview of Quota Composition for the 12 Processes

Table 1 summarizes the table lookup parameters, correction factors, and preparation and finishing times, serving as the index for the entire standard.

Table

No.ProcessTable Lookup ParametersMain Correction FactorsPreparation and Finishing Time
1Lathe WorkOuter diameter × length; for sleeve-type parts: length, model, inner diameterBatch coefficient, material coefficient; sleeve-type boring of inner bore K=1.210′
2MillingLength × width (face milling); groove depth, groove width, groove length (groove milling)Batch coefficient, material coefficient; milling internal cavity K=1.510′
3Bench WorkHole depth × hole diameter (drilling and tapping); area, outer diameter or inner diameter × length (polishing); R × diameter (R chamfering)Drilling only or tapping only reduces by half10′; R chamfering with polishing 10′
4Hand-Operated Surface GrindingPart overall dimensions and part typeCannot process simultaneously 0.8; can grind simultaneously 0.2~0.5Per remarks in each entry
5Coordinate GrindingHole diameter × hole depthHigh-precision holes 1.7~2; hardened parts +10′Fewer than 50 holes 30′; more than 50 holes or repositioning/flipping 60′
6Cylindrical GrindingOuter diameter × lengthMaterial 1.3; batch 0.8 (single piece 0.7); precision 0.7~1.2Setup 20′/piece
7Internal Bore GrindingInner diameter × lengthFour items: material, tolerance, batch, familiarity10′; grinding outer diameter with mandrel adds 30′
8Surface GrindingLength × width (grinding six faces); machined area (grinding four flat surfaces)Unhardened 0.7; aged rough 0.7, finish 0.3; tolerance 0.7~1.2; batch 1~0.15—
9Slow Wire CuttingCutting area and number of cutting passesThickness less than 10mm multiply by 1.3~2.0; straight cutting edge section and blanking taper 1.330′; two clamping operations or aligning prior precision holes 60′
10EDM (Small Hole Drilling Machine)Hole depth × hole diameter; thread specification—Thread setup 10′
11Fast Wire CuttingCutting area (mm²)Material (steel parts, carbide) and machine model10′; finish machining of continuous cavity 30′
12CNC Machining CenterHole diameter × plate thickness; counterbore diameter and depth; bore diameter, depth, and tolerance; curved surface and cavity areaMaterial hardness, form tolerance30′ per clamping

IV. How to Calculate Work Hours Quota? The Five-Step Method

Step 1: Look up basic work hours. Look up the corresponding quota table based on the process and the main dimensions of the workpiece. Lathe work uses outer diameter and length (sleeve-type parts use length, model, and inner diameter); milling uses length and width (groove milling uses groove depth, groove width, and groove length); bench work uses hole depth and hole diameter, polishing area or diameter and length; coordinate grinding uses hole diameter and hole depth; cylindrical grinding uses outer diameter and length; internal bore grinding uses inner diameter and length.

Step 2: Multiply by correction coefficients. Take values separately according to processing material, batch size, tolerance and surface quality, and product familiarity; when multiple coefficients apply to the same process,multiply them in sequence, not add them.

Step 3: Add preparation and finishing time. Most processes are 10 minutes, added separately outside the single-piece work hours; coordinate grinding is 30 or 60 minutes based on hole count; cylindrical grinding setup time is 20 minutes/piece; CNC machining center is 30 minutes per clamping.

Step 4: Add auxiliary work hours. Threads, center holes, chamfers and R chamfering, cutoff, and abutting step end faces are added per the remarks in each table,without duplicating the basic work hours.

Step 5: Round according to a unified rule. All values in the tables arerounded downbased on the calculation results: tables with whole-minute increments round to the nearest minute (e.g., 16.1 is recorded as 16, 10.9 is recorded as 10); in calculation examples retaining one decimal place, round to 0.5-minute increments (e.g., 10.56 is recorded as 10.5). The same process and the same table must consistently use the same rounding rule and must not mix methods.

V. Why Can Work Hour Quotations for the Same Part Differ by a Factor of Two? The Four Types of Correction Coefficients

The difference usually does not lie in the table lookup stage but in the coefficient stage. The value ranges for coefficients across processes are as follows:

Table

ProcessMaterial CoefficientBatch CoefficientPrecision/Tolerance CoefficientFamiliarity Coefficient
Lathe Work0.8~1.2 (non-ferrous metals 0.8, A3/40Cr/45 is 1, Cr12MoV/Cr12/P20 is 1.1, P21/V10/ASP23 is 1.2)1.1~0.5 (1~4 pieces 1.1, 5~20 pieces 1, 21~50 pieces 0.8, 51~200 pieces 0.7~0.5)Supplemented via auxiliary work hours—
Milling1~1.2 (ordinary steel 1, Cr12MoV/V10/9SiCr is 1.2)1~0.7 (1~3 pieces 1, 4~10 pieces 0.9, 11~30 pieces 0.85, 31~50 pieces 0.8, 51~100 pieces 0.7)Groove milling with precision requirements 1.2~1.5; internal cavity milling allowance T is 1~4.5—
Internal Bore Grinding1~1.4 (45#/P20/A3 is 1, Cr12/SKD11 is 1.2, SKH51/ASP23 is 1.3, carbide 1.4 only for finish machining)1~0.7 (single piece 1, within 5 pieces 0.9, 5~20 pieces 0.8, above 20 pieces 0.7)Above 0.02 is 0.8, 0.02 is 1, 0.01 is 1.1, 0.005 is 1.2New type 1, relatively familiar 0.9, mature 0.8
Surface GrindingUnhardened parts 0.7; aged rough grinding 0.7, finish grinding 0.31~0.15 (1~2 pieces 1, 3~5 pieces 0.7, 6~15 pieces 0.5, 16~30 pieces 0.35, 31~50 pieces 0.2, 51~100 pieces 0.15)Light finish 0.7, 0.1 is 0.8, 0.05 is 0.9, 0.02 is 1, 0.01 is 1.1, 0.006 is 1.2—
Cylindrical Grinding1.30.8 (single piece 0.7)0.7~1.2—
Coordinate Grinding——High-precision holes 1.7~2—
Slow Wire Cutting——Thickness less than 10mm multiply by 1.3~2.0; straight cutting edge section and blanking taper 1.3—

Key Rule Reminder: Sleeve-type parts (Table 5)do not reference the batch coefficient table; regardless of batch size, they are calculated as single-piece basic work hours multiplied by the material coefficient. When milling machines clamp multiple parts simultaneously, increase the total length-based work hours by 25%. When CNC boring holes of the same type exceed 10, multiply the base by 0.5.

VI. Key Quota Data for the 12 Processes

6.1 Lathe Work

For external cylindrical turning, look up Table 4 by outer diameter D and machining length L, with single-piece work hours ranging from 2 to 12 minutes; there is also a “step ≤8” column specifically for step sections with length not exceeding 8mm, taking 2~3 minutes. Sleeve-type parts are looked up in Table 5 by A/B/C three types, length, and inner diameter, with 10~130mm lengths corresponding to 7~65 minutes. Additional remarks: threads add 3~5 minutes per piece, center hole drilling adds 1.5 minutes per end, grinding both center holes adds 3 minutes, taper shank coefficient is 1.2, and slender shaft coefficient is 1.5~3.0.

6.2 Milling

Face milling is looked up in Table 8 by length and width, from 4 minutes for 50×25mm to 70 minutes for 1100×350mm, with values representingsingle-face millingwork hours. Internal cavity milling multiplies the face milling work hours by K=1.5, then applies a finishing coefficient of 1~4.5 based on allowance T. Groove milling is looked up in Table 10 by groove depth, groove width, and groove length, with 12~20mm deep grooves at 15~65 minutes and 20~40mm deep grooves at 35~95 minutes.

6.3 Bench Work

Tapping and drilling are looked up in Table 11 by hole depth and hole diameter, with values combining drilling and tapping; tapping only or drilling only reduces by half. For small and medium-sized threaded holes in plates within 25mm thickness, including preparation time, each thread can generally be estimated at 3 minutes. Lapping and grinding flat surfaces is looked up in Table 12 by area (10cm² is 22 minutes, 600cm² is 90 minutes). Polishing external cylindrical surfaces is looked up in Table 13 by outer diameter and length (3~15 minutes), and polishing internal bores is mostly 10 minutes. R chamfering with polishing is looked up in Table 15 by R value and diameter (1~20 minutes).

6.4 Hand-Operated Surface Grinding

Grinding six faces requires perpendicularity of 0.005 across all six faces: parts of 50×50mm or smaller with allowance 0.3~0.4 generally take 35 minutes; parts of 100×50mm with allowance 0.3~0.5 generally take 60 minutes. For batch production where parts cannot be processed together, multiply by 0.8; for smaller parts that can be ground together, multiply by 0.2~0.5.

6.5 Coordinate Grinding

Setup time is based on hole count: fewer than 50 holes is 30 minutes, more than 50 holes or requiring repositioning/flipping is 60 minutes. Individual holes are looked up in Table 17 by hole diameter and hole depth (allowance 0.3~0.4, material 45#/P20, etc.), ranging from 12 to 45 minutes. Listed dimensional precision is 0.01~0.02 with surface roughness Ra0.8; high-precision holes with Ra0.4 or tolerance within 0.005 multiply by 1.7~2; hardened parts add 10 minutes based on the table value; plates around 30mm thick can be estimated at an average of 20 minutes per hole (including preparation).

6.6 Cylindrical Grinding

The data in Table 18 represent thecombinedrough and finish grinding work hours, split as 45% for rough machining and 55% for finish machining, with machining allowances divided into three tiers of 0.3~0.4, 0.5~0.6, and 0.7~0.9, ranging from 8 to 50 minutes. Setup time is 20 minutes per piece.

6.7 Internal Bore Grinding

Look up Table 20 by inner diameter and length, with work hours ranging from 30 to 115 minutes, also representing the combined rough and finish grinding total (45%/55%); after lookup, apply the four coefficients of material, tolerance, batch, and familiarityitem by item. Notes: abutting a step end face adds 1 minute per location; grinding the outer diameter with a mandrel adds 30 minutes of setup time.

6.8 Surface Grinding

Grinding four flat surfaces is looked up by machining area and tolerance, with additional material and batch coefficients; when more than four faces require parallelism and perpendicularity of 0.01, add 10~15 minutes, and for 0.005 requirements, add 15~20 minutes. Grinding six faces is looked up in Table 24 by length L and width B, applicable to parts with thickness of 10~60mm, with 50×60mm at 25 minutes and 1200×380mm at 360 minutes.

6.9 Slow Wire Cutting

Work hours are calculated by cutting area, with cutting speed decreasing as the number of cutting passes increases: single cut at 70mm²/min, one cut with one trim at 28~32, one cut with two trims at 21~23, one cut with three trims at 19~21, and one cut with four trims at 18~20. The correspondence between precision and number of passes is: tolerance above ±0.02 requires one cut, ±0.01 requires one cut with one trim, ±0.003 requires one cut with two trims, and ±0.002 requires one cut with three trims. For thickness of 18~50mm, take the upper limit value; for less than 10mm, multiply by 1.3~2.0.

6.10 EDM (Small Hole Drilling Machine)

Look up Table 26 by hole depth and hole diameter: hole depth less than 15mm with hole diameter 0.3mm is 5 minutes, and hole diameter below 0.2mm is 12 minutes; hole depth of 81~90mm with hole diameter 1.0mm is 28 minutes. For thread machining, look up Table 27 by specification: with pre-machined pilot holes, M4~M8 is 20 minutes and M10~M12 is 60 minutes; for thread machining, M4~M5 is 40 minutes, M6~M8 is 30 minutes, and M10~M12 is 50 minutes; setup time is 10 minutes, and machining depth is 8~10mm.

6.11 Fast Wire Cutting

Setup time is generally 10 minutes; for finish machining such as cutting continuous cavities, it is 30 minutes; when cutting-to-length work hours exceed 30 minutes, no setup time is applied. The rest is calculated by cutting area: for Shanghai and Taizhou machines, steel parts are 40~45mm²/min and carbide is 20~25mm²/min; for Baoma machines, steel parts are 50~60mm²/min and carbide is 25~30mm²/min.

6.12 CNC Machining Center

Drilling is looked up in Table 29 by hole diameter and plate thickness: Φ2~5mm in 5~15mm plate thickness is 0.6 minutes, Φ35~45mm in 45~55mm plate thickness is 11 minutes, plate thickness above 55mm increases proportionally, plus (number of hole types ×3) minutes. Counterboring adds (number of types ×3) minutes. Boring is divided into three tables by tolerance (above 0.05, 0.02~0.05, within 0.01), plus (number of types ×10) minutes, and when holes of the same type exceed 10, multiply by 0.5. Curved surfaces are calculated at 1.5~4 minutes per 100mm², and cavities and grooves are calculated at 0.7~3 minutes per 100mm² of side area. The work hours formula for core rods on manifolds is “number of grooves × coefficient + 120 minutes”, with a coefficient of 10 for D30 and below, 15 for D30~D40, and 20 for D40 and above.

VII. Three Calculation Examples: The Complete Process from Table Lookup to Rounding

Example 1: Lathe work, one-pull punch for household air conditioner mold

Batch of 24 pieces, material Cr12MoV. Look up Table 4 for single-piece work hours (step ≤8 takes 2 minutes, length tier takes 5 minutes), take batch coefficient 0.8 from Table 2, material coefficient 1.1 from Table 3, and add R chamfering and cutoff at 2.5 minutes:

T = [2×1.1 + 5×1.1 + 1.5×2 + 2.5] × 0.8 ≈ 10.5 (minutes)

Preparation and finishing time of 10 minutes is added separately per the remarks.

Example 2: Lathe work on sleeve-type part, four-pull die for household air conditioner mold

Batch of 24 pieces, material Cr12. Sleeve-type partsdo not reference the batch coefficient table; look up Table 5 for basic work hours of 11 minutes, take material coefficient 1.1 from Table 3, and add auxiliary work hours of 4 minutes:

T = 11×1.1 + 4 ≈ 16 (minutes)

Example 3: Milling, centerless grinder guide plate

Batch of 50 pieces, material P20. Look up Table 10 for groove machining work hours (10 minutes × 2 pieces, 5 minutes × 2 pieces), and add other work hours of 20 minutes:

T = 10×2 + 5×2 + 20 ≈ 50 (minutes)

This example is a summary of groove machining table lookups anddoes not include the batch coefficient; in actual execution, it should be converted separately using the batch coefficient.

Example 4: Cylindrical grinding, rough and finish grinding calculated in tiers

Table

Machining ContentFormulaSingle-Piece Work Hours
Rough grinding two outer diameters abutting end face(4+4)×1.3×0.8×0.7+17′
Finish grinding two outer diameters(5+5)×1.3×1.2×0.710′
Rough grinding 5.6 inner bore35×1.3×1.2×0.7×0.4517′
Finish grinding 5.6 inner bore35×1.3×1.2×0.7×0.55×0.817′

The four formula results are 6.82, 10.92, 17.20, and 16.82, rounded down to 7, 10, 17, and 17. Each piece adds 20 minutes of setup time.

VIII. How Is This Quota Standard Used in Quotation, Production Scheduling, and Assessment?

  1. Quotation: Look up the quota for each process along the part's process route, multiply by coefficients, accumulate auxiliary work hours to obtain single-piece work hours, then multiply by the hourly rate and add material, outsourcing, and management costs. With a unified work hours basis, quotation differences only come from rate and profit strategies, not from “whose master estimated more aggressively”.

  2. Production scheduling: Accumulate process quotas to obtain equipment load, and schedule delivery dates in reverse order based on bottleneck equipment. The batch coefficient directly reflects “doing more in the same batch saves time,” serving as the basis for evaluating rush order insertion.

  3. Assessment: Use the quota as the denominator to calculate the achievement rate. Since the quota is recomputable, overtime work hours have a clear direction for cause analysis — check the table lookup, coefficients, and preparation time one by one.

IX. Frequently Asked Questions

Q1: What is the unit of mold work hours quota?Minutes. Values in the tables followed by “′” are in minutes, and all values represent single-piece machining work hours.

Q2: When multiple coefficients apply to the same process, are they added or multiplied?Multiplied, in sequence. For example, for 24 pieces of Cr12MoV parts in lathe work, material coefficient 1.1 and batch coefficient 0.8 are multiplied together, not added.

Q3: Is preparation and finishing time included in the table values?No. Most processes add 10 minutes separately; coordinate grinding is 30 or 60 minutes based on hole count; CNC is 30 minutes per clamping; cylindrical grinding setup is 20 minutes per piece.

Q4: What if the corresponding size cannot be found in the table?“—” indicates it is not specified, andinterpolation or extrapolation is not permitted; it should be evaluated by process personnel referencing similar specifications, with the basis for the value noted in the process documentation.

Q5: Is rounding done to the minute or to 0.5 minutes?Two rounding rules are used by table: tables with whole-minute increments round down to the minute (16.1→16); calculation examples retaining one decimal place round to 0.5-minute increments (10.56→10.5). The same process and the same table must not mix rules.

Q6: Why is the batch coefficient not applied to sleeve-type parts?The standard explicitly stipulates that Table 5 does not reference the batch coefficient table. Sleeve-type parts are calculated as single-piece basic work hours multiplied by the material coefficient regardless of batch size, which is an important distinction from other lathe-worked parts.

Q7: Can this quota standard be directly applied to other mold factories?The standard is intended for calculation, quotation, production scheduling, and assessment within the group's mold manufacturing and related operations. External enterprises may refine it within its framework based on their own equipment conditions, but the refined quota level shall not be lower than this standard.

模具工时封面.jpg

X. Standard Information

Table

ItemContent
Standard NameMold Enterprise Work Hours Quota Standard
Standard NumberQ/FT 27.66.20261106
VersionV27.0
Issuing OrganizationFangtian Software Group
Date of IssueNovember 8, 2026
Date of ImplementationDecember 1, 2026
Drafting OrganizationFangtian Software Group Xi'an R&D Center
Principal DrafterLi Zhixian
Structure and Scale13 chapters, Tables 1 to 35, covering 12 processes

This standard is proposed and managed by Fangtian Software Group, with the Group's standardization management department responsible for interpretation; if revisions are needed during implementation, user units shall collect comments and submit them to the Group's standardization management department for unified handling.

About Fangtian Software Group

Fangtian Software Group is a domestic industrial software supplier focused on manufacturing, with the mold industry as its core赛道. It is a national-level specialized and innovative “little giant” enterprise, and the originator and trademark holder of the MoldERP (Mold Enterprise Resource Planning System) concept. The company started in Taiwan in 1996, formally entered the mainland market in 2000, and was listed on the National Equities Exchange and Quotations (NEEQ) in June 2018. With nearly 30 years of dedication to manufacturing digitalization, it adheres to a niche market strategy, focusing on the management pain points of single-piece, small-batch, non-standard discrete manufacturing.

The "Mold Enterprise Work Hours Quota Standard" is a systematic accumulation of transforming mold industry process experience into recomputable data assets: work hours are no longer experience values passed down orally by masters, but engineering parameters that can be looked up in tables, verified, and aligned across factory sites.


share
Next:This is the last one
Prev:This is the first article